Search This Blog

Thursday, March 18, 2010

EXPERIENCE BEAUTIFUL WILDLIFE ON YOUR DOORSTEP



Bringing a local park into the 21st Century and ensuring the continued wellbeing of its native wildlife is not as simple as you may think.

Take Queen’s Park in Crewe as an example; Cheshire East Council (CEC) is currently investing £6.5m into restoring the park to its former glory but have also been tasked with meeting the demands of certain feathered visitors and the park’s more permanent resident: bats.

The bats, four different protected species, have made the existing bandstand area their home over the past few years and seemed contented to stay put. However, for human visitors, the old, leaky roof had become somewhat of an eyesore. A series of surveys identified when the bats would leave the site to roost elsewhere. At this point the roof was refurbished and pieces of plywood suspended from the ceiling to provide more suitable accommodation for these flying mammals.

Cheshire East Councillor Andrew Knowles, Cabinet Member with Responsibility for Parks, said;

“This is proof that the numerous surveys which have been carried out to protect wildlife in the park are paying off. Improving life for birds and bats as well as ourselves is the main aim of this project. The work which has been completed has already revitalised the area. This can only continue as the project nears completion.”


Case Study, Mark Stubbs – A member of the South East Cheshire Ornithological Society, said:

“I recently decided to pay a visit to the Queen's Park in Crewe to see what birds were present. Having spent the last few years conducting bird surveys in the urban Crewe area, surprisingly I hadn't visited the park, so it was something I had to do for curiosity's sake.

“I arrived at the entrance opposite Tipkinder Park and immediately saw a Coal Tit. Next I saw a Jay, in my opinion, one of our most beautiful resident
birds. Wood Pigeon, Collared Dove (picture left), Mistle Thrush, Great Tit and Blue Tit soon followed. A Tree Creeper climbing up a tree by the play area continued a good start to the walk and as I proceeded, resident songbirds were in evidence, such as Robin, Wren and Dunnock.

“All of a sudden, the unmistakable undulating flight of a Greater Spotted Woodpecker overhead was noted before it landed in a treetop. Blackbirds and Song Thrushes, which were worming on the grassed areas, were joined by several Redwings. There have been large numbers of this Scandinavian thrush in the UK this winter, and birds are not only turning up in parks, but in gardens as well.

“At the Victoria Avenue entrance, House Sparrows were chirping on the Gatehouse buildings and in the adjacent area, Magpie, Crow, Jackdaw, feral Pigeon and Pied Wagtail were noted. Chaffinch, Greenfinch and Goldfinch were soon added to the list and then I heard a Goldcrest. After a minute or so it gave itself up, flicking away in the foliage, looking for insects. It's amazing how this, our smallest British bird, survives considering we've just experienced our harshest winter in over thirty years.

“In the lake area I saw approximately 70 Mallard along with a single male
Mandarin Duck. Originally one of a breeding pair present since 2000, the male has been on his own since 2003, and resident ever since. Fifteen Canada Geese, a single feral Greylag Goose, with the farmyard type white geese, four Moorhen and a grey Heron were also seen, along with 15 Black-headed and two Common Gulls, hanging around, hoping for an easy meal when people come to feed the ducks bread.

“So, it just goes to show that you don't have to visit the countryside to experience bird life when it's on your own doorstep!”

There have been more additions to the park to ensure Queen’s Park remains a ‘des-res’ for all manner of local wildlife. These include a number of nest boxes:

10 Tit boxes – various size entrance holes, 25mm-32mm;
2 Treecreeper boxes;
2 open fronted boxes;
1 larger box – 45mm entrance hole;
1 Hawk box and;
1 large owl box;

There are plans to erect more boxes in the future, including 2 owl chimneys.

Another habitat booster that has been introduced over the last two years is the creation of small discreet log piles. Sometimes, this may just be one large log or bough, placed within a shrubbery. The decaying wood attracts fungi and insects, the latter providing a good food source for many other animals.

Plus, the more unusual....

The Mandarin Duck, referred to by Mark Stubbs is an uncommon feature around Britain’s parks, but one permanently resides in Queen’s Park and his late family members before him since 1980. Plus, a more recent welcome visitor is the Cope Shields Duck, seen numerous times over the last two weeks; it is thought to have either escaped or been set free as it is not a native of these shores.

Information concerning Queens Park can be obtained by telephoning Elaine Dodd, Queens Park Manager on 01270 537559.

Wednesday, March 17, 2010

Second Burma Bridge Arrives

The second Burma Bridge arrived to day just one week after the last one This time a heavier crane was need to get the bridge into place
View of the new bridge from the far side of the lake (Morton rd end) so you can see what the two bridges now look like. Notice the wall around the lake which has been completed


The crane lifting the bridge into place. next week is the big week when the long awaited Broadwalk bridge comes. As its so big this will take 3 days starting Monday when the steel support will arrive and this will have to be welded on site. Its hoped to have the bridge in by Wednesday ready for the Friends meeting which is on Wednesday at 6 o'clock at the cafe everyone is invited to attend.
There is now like 2 weeks for the contractor on site and the job will be finished its hoped the same firm will get the contract for the new cafe as they are already on site and can start straight away.

Thursday, March 11, 2010

Burma Island Bridge

More pictures of yesterdays bridge which is now full installed. Above the bridge from the lake Tipkinder end

The new bridge from across the lake Morton road end taken with a Fugi S1500 12X Zoom
The bridge taken from the Gold Coarse with the island in the foreground which is being renovated you can see that its being heightened a lot to match other Islands

The Island near Tipkinder now renovated and dug over ready for the new planting any day now

Another visitor to the park the South African Shelduck seen walking about the park

Wednesday, March 10, 2010

Burma Star Bridge Spectacularly Lifted into Place


The Burma Star Bridge – the second largest landmark bridge in Crewe’s Queens Park – was hoisted into place on Wednesday (March 17)
From 11am onwards, A 300 tonne crane lifted the 22.5 tonne bridge into place.
The Burma Star Bridge – named so after the Second World War Campaign in the Burma jungles – will arch over the Burma Star Island and Memorial, which is also undergoing renovation.
It’s all part of a £6.5m restoration of the park, thanks to the Heritage Lottery Fund. Eventually, the 45-acre park will house five impressive bridges.
Councillor Andrew Knowles, Cabinet member with responsibility for parks, said the special occasion was close to his heart.
His uncle, James Knowles, who served as a Chindit during the Burma campaign, died in 1944 aged just 20 years-old. To this day, Andrew has kept a medal he won as a keepsake.
He added: “This will be an important part of Crewe’s history when this bridge finally settles into place.
“This incredible Victorian park is slowly being brought back to its former glory thanks to Cheshire East Council and its funding partners, as well as all the help and support from members of the public who have been extremely patient during renovations.”
The Burma Star Bridge is a tribute to the Burma Star Association who refer to themselves as the “Forgotten Regiment”.
The Burma Star Association was officially founded on the 26 February 1951, with 2000 founder members who exist to promote the comradeship experienced during the bitter fighting in the jungles of Burma, as well as help members and their families in times of ill-health and poverty.
The Association has representatives from the Royal Navy, Army Royal Air Force and Royal British Legion on the National Council.




The bridge being lifted with the steel work. Most of the work was done by 3pm but the second part of the bridge hadn't arrived at that time
What the bridge will look like when the lake is filled
Besides the bridge the new wall near Burma Island was going in around the lake

Further down the new wall by the golf coarse was cracking on as well.

More pictures soon as there is a lot happening at the moment

Thursday, March 4, 2010


Click on the picture to see it full screen

A progress report on the state of play at the park. Details have been announced of when work will be done and finished.

Work done so far is Dredging, Tree removal, Railings, Bandstand and Drain repair.

Work to be competed by June 2010 Bridges and Lake, New Play Area. Planting on the Islands

Work to be done by June 2011 Footpaths, New Depot Main Pavilion, Bowls pavilion, Lodges and Clock, Boer War Memorial, Gates and Coronation Walk

The last of the footing for the Broad walk has now been done ready for the new bridge


A lot of work has been done this week on walls around the lake above is Burma Island wall almost completed and the bank wall leading to it from Tipkinder
Work on a new section of wall near the new bridge was well underway today and the top stones on the islands were going on. Planting of the islands is expect in the next couple of weeks subject to weather

Friday, February 26, 2010

Snow progress


Progress has been slow at the park this week due to snow, frost and rain. The stones for the top of the wall were due to be done but couldn't be done with it freezing. There has work been done on the Broadwalk as the template for the bridge is being framed ready for concrete.

A lot of the hardcore 800 tons that was used to get the bridge in last week is being removed to be used in other parts of the park.



Burma Island has been cleaned up ready for the bridges and planting and work on the other islands has gone ahead ready for being planted.

Our friendly rare Mandarin duck is still strutting about the park and looks a bit like Roadrunner keep your eyes open for him.

Wednesday, February 17, 2010

Second Bridge arrives at Queens Park


The second bridge arrived at the park today. It taken all week to lay over 800 tons of hardcore in order to get the crane and bridge on site with over 300 tons just for the crane. Its not the biggest bridge but as it has steep paths to it there was difficulty getting a massive lorry and crane down to the site.

It started at about 11 o'clock when the steel work came first and was lifted into place as we all held our breath. As it was built off site and the tolerance was in millimeters would it fit? Well it was perfect right down to the bolt holes. The steel had struts on it so two parts could be lifted at once. It took to about 1:30 to bolt the steel in place.

The bridge then came on site being reversed down a steep hill on a big lorry this was a good bit of driving on the drivers part with only inches to spare. The bridge was split into two parts and lifted into place with no problems. It gives a good idea of what the new bridges will look like when its all finished. The next bridges for Burma Island are expected about 17th March

The steel structure in place waiting fro the bridge
The bridge arrives on the lorry ready to be lifted
The first section being lifted into place

The second section is lowered spot on
The bridge complete with just some boards to go on it.

While we were watching the bridge we caught site of the rare mandarin Duck swimming in the lake I had not seen it for a couple of weeks since I last took its picture but its still here
Work was also going on around Burma Island to build up the base to the new wall the new coping stones for the lake walls are expected next week when there will be lots of bricklayers on site to get them laid

Friday, February 12, 2010


The wall around Burma island has been built for most of this week

The second landmark bridge is to be installed at the historic Victorian, Queens Park, in Crewe next week.

The bridge is 14.5 metres long and is supported by tubular steel with timber beams, decking walkway and handrails.

Last month the very first bridge, Tipkinder, was installed to a fanfare of media and public attention and Coronation Bridge is promised to be even more impressive.

The media are invited to witness this historic installation on Wednesday, February 17 from 12 noon. The installation is expected to last throughout the afternoon. Please come to the Tipkinder entrance off Queens Park Drive.

Members of the public are also being encouraged to come along and witness history before their eyes. For those who want to get a close-up view please call the park manager, Elaine Dodd, on 01270 537896 so she can arrange a public viewing area.

Works:
To allow these extensive works to be carried out, around two thirds of the park have been closed off to the public, but it’s hoped that three quarters of the park will have been re-opened by the end of the year.
Other works in the pipeline include a planning application for replacement buildings, the largest of which is the new pavilion to replace the Jubilee Cafeteria built in the 1970s.

Modern in design, it will be made out of sandstone and glass to give customers impressive views over the park’s grand grounds.

Planning permission for a new bowling pavilion is currently under-way and designers are in talks with the Queens Park Bowling Club to get the best facility possible. Both buildings will have newly refurbished public toilets.

Derek Morgan, Chairman of the Friends of Queens Park Group, said, “Things will start to move very quickly during the Spring and Summer months. People will start to see a real difference as the Park is brought back to its former glory”.

The East and West lodges will also be improved and up-dated and there are plans for a “Memorabilia Lounge” at the West lodge.

Councillor Roy Cartlidge, of the Crewe West Ward, who has supported the project throughout, added, “The installation of the main bridges will be a significant part of the Park’s history and are intended to last the next hundred years and beyond. “

Tuesday, February 9, 2010

FRIENDS UPDATE FEBUARY 2010


photo the old bridges in the 1960

The meeting this time was a short one but well attended despite the cold weather. Matter raised were trying to get a webcam and Wifi for the park and the development of the play area. Most other things were covered by the chairmans report below

Friends Chairpersons Update:
a. Bandstand Completion
b. ‘New’ Buildings Package / Planning Consent
c. Works in Progress

a. Bandstand:

Lost Art are in the final stages of the completion of works. Approx 80% has been finished as can be seen. Predictable delays to finalizing stone work due to ground frost, completion any time now.

b. New Building Package:

Three Planning Applications have been submitted – 1. The new Cafeteria; 2. Bowling pavilion and 3. Depot building. Consent for all 3 is expected by mid March. Will probably result in closure of cafe sometime during the summer months, mobile catering arrangements will be arranged to enable a service of light refreshments.

c. Tolent Works

Tolent have been on site for 20 wks following acceptance of the contract.

Works have focused again on lake edges and islands plus preparations for bridge abutments and foundations etc.

The Inlet Bridge at the TipKinder end of the lake was installed on 27th January about 1.30pm.
This will be followed by the installation of the Coronation Bridge next Wed 17th, which will be installed in 3 sections. Probably from mid morning on the 17th through to mid pm. on the 18th.

This will be followed by the installation of the Burma Star bridges (x2) and the Broadwalk Bridge.

65% of the lake edge preparation wall works have been completed with only the West side of the island to finish. Approval of materials for coping stones is to be confirmed this week.
There is some extensive work to access roads to be done, to support the large cranes needed to ‘swing’ the bridges into place.

It’s good to see that last week and this week the Park is a hive of activity with 19 men from Tolent on site working on the lake edges and bridges with 15 also remaining on site this week. Five men from Lost Art are working on the completion of the bandstand and a team of 3 park gardeners have been clearing weeds and overgrown vegetation from the Coronation Walk Valley in preparation for the next contract package.

The cold weather has caused some delay however the contractor is aiming to catch-up as much as possible with bridge installations taking place almost back-to-back.

The bridge fabricators are working very well off-site as will be seen by those visiting the factory in Huddersfield next Tuesday.



Filling of the lake is anticipated by the end of the summer subject to unknown obstacles.

I would like to introduce you to Dave who has kindly attended from Tolent Construction – the main contractors on site; should anyone here have any technical questions or issues they wish to raise. (Open to floor). Thank you Dave.

Work in Progress:

We are all eager to see the PG works commence and consultation with Sir William Stanier School has continued. An expression of Interest notice on the CE web site attracted 34 contractor responses. This has been whittled down to 6 potential suppliers. The disabled requirement has yet to be confirmed from the consultation with the additional funding sourced from an ex-C&NBC Mayor.

The project will take 3 forms, appealing to all age ranges. Toddler Equipment, Youth Equipment and Equipment for All Ages i.e. Outdoor Gym style. Some works may be subject to further external funding which the Project Officer is pursuing.

A copy of the children’s presentation which is being used to draw up the specification is available.

Further funding:

Additional Wren bids are being prepared to support additional works identified:

• Computerised irrigation system to facilitate more efficient bowling green maintenance
• Lake Water aeration system and improvements to inlet and outlet mechanisms
• Play Ground Outdoor /Gym and possibly installations over 4m high.

Item 7
Visit to Bridge Fabricators

5 Places remain on the coach for anyone wishing to attend next Tuesday leaving QP Lodge at 10am. Seats will be allocated on a first come first served basis – does anyone here wish to attend please – it will be a very interesting day for all?

Item 8
Events List 2010

Copies of programme available.