Broadwalk Bridge

A massive crane was on site today to finish lifting the final part of the bridge into place
There had been problems last week when the crane refused to lift as the wind was to high but with today being a nice day all went well


The final piece goes in and the rails and cross member have now to be installed

Island Planting

The second island is being planted and the gardeners are working hard to finish it. That is two island now planted with only Burma Island left to plant
The main entrance is a spectacle of Spring color and well worth a visit

Thursday, April 8, 2010

Broadwalk Bridge Update

Unfortunately, there has been some delays through the weather causing concerns with this installation which remains underway.As you now it was hoped to complete the installation around Easter so we are about 1 week behind.

Health and safety considerations means the large crane cannot operate with winds 25+mph. Last week these averaged 23mph and so was too close to the tolerance for installation.

The good news is the first section is in. It is anticipated the second section will be Thursday of this week, weather permitting – winds forecasted at 12mph at this time. Unfortunately, there was no crane availability to rearrange for today.It will take probably a week to install and complete, with the decking the week following.

Contractors remain on site and are top soiling the lake edges at this time. Also, they are finishing the installation of the handrails on the Burma Star Bridges; additionally they are working with our gardeners to enable the West Island to be planted up this week.

But as you can see there are some good floral displays at the park with spring bedding now in full bloom

The wall on the lake is nearly finished and the island near the golf coarse is ready for planting any time now

Tuesday, March 30, 2010

Broadwalk Bridge


The Island planting near Tipkinder is now complete and the gardeners will be moving onto the other Islands to prepare them for planting


The second section of the bridge is in and they are putting the decking on. The rest of the section are being put on hold until Tuesday as the strong winds are giving problems with the crane

Monday, March 29, 2010

Broadwalk Bridge



The bridge over Broad walk was being put into place today but due to the size and complexity they were having trouble getting it to fit. They had to take it out and put it back a few times and by 3 o'clock they only had the first section in and it looks as if it will continue tomorrow.



The Daffs our now coming out along the main walk at a rapid pace


Lots of gardeners were out planting the island today as it needs to be done before any water is in the lake.

Friday, March 26, 2010

Broadwalk Bridge



As reported the other day they had trouble getting the giant steel support into and in the end it had to be done the next day. It was just down to a safety computer on the crane which wouldn't let it lift the steel as it was to windy.
However on Thursday the wind had dropped and the support was in place.


There is now some work to do on site welding the top supports onto the steel and as you can see in the above picture that is now going ahead the bridge its self which you can see in the background will be lifted into place on Monday as the men are working over the weekend to get everything ready


The metal supports for the end of the bridge were lifted into place. The work will then be completed by Thursday night when all the bridges will be fully installed. One of the Burma Bridges has yet to be lowered a few feet after the initial settling period. The contractor Tolent will then be leaving the site after Easter but its hoped they will get the Cafe contract so they can start work straight away

Tuesday, March 23, 2010

Whats on in the Quens Park this year

Broadwalk Bridge



Work Started today trying to get the giant steel work in for the Broadwalk bridge which will be lifted into place on Thursday. They managed to get the base fixed with little problems. But then the giant crane hit a snag it has a computer control which measures the wind speed and it would not let them lift as the wind speed was to high. They needed to lift the massive steel supports very high over the trees in order to lower it into place but by 3 o'clock they still couldn't do it due to high wind speed. I have know doubt they lifted it in the end but we watch for several ours as they kept trying only to be defeated by the computer and weather. More reports tomorrow

Friday, March 19, 2010

Queens Park Grandest Bridge To Be Lifted Into Place


Picture the new massive steel structure on site on Friday ready for installation on Monday

Another milestone in the multi-million pound restoration of Crewe’s Queens Park takes place next week with the installation of its grandest bridge.

Following this week’s positioning of the Burma Star Bridge, Thursday (March 25) will see the 40-metre Broadwalk bridge hoisted into place over the Coronation Walk dip.

The structure, which is six metres wide, will span the steep incline to improve access between the two halves of the park.

A giant crane will lift the arches in four separate pieces and install them on a huge steel central support.

The bridge beams are constructed of sustainable ekki hardwood, a longer-lasting timber which reduces the pressures of logging on the forests of the world.

Self-preserving and with self-repairing properties, its timbers can only be machined as the wood is too tough to work with hand tools.

The new structure is the latest development in the Heritage Lottery-funded £6.5m restoration of the 45-acre park, which will eventually house five impressive bridges.

Councillor Andrew Knowles, Cabinet member with responsibility for health and wellbeing, said: “The lifting into place of the Burma Star Bridge was a sight to behold and I am sure the Broadwalk installation will be just as spectacular.

“The new bridge will be a very impressive structure and will be particularly welcomed by people with pushchairs and wheelchair users, who will no longer be forced to negotiate the steep incline.
Below the last bridge on Burma island now fully installed



“The park restoration is really gathering pace now thanks to the hard work of the design team whose members are seeking to complete works ahead of schedule wherever possible.

“Over the coming months, park users will notice more big changes as more areas re-open to the public.”

The next stage in the restoration will be the completion of the lake edges and bed, with the filling of the lake scheduled for summer.

The design and selection of the new playground equipment - in conjunction with Sir William Stanier School - is currently being finalised and will be installed in time for the school summer holidays.

Anyone who would like to find out more about the restoration is welcome to attend the next meeting of the Friends of Queens Park this Wednesday (March 24) at 6pm in the park cafeteria.

Regular updates are available by mail. Please contact Queens Park Manager Elaine Dodd on 01270 537896 to register your details.